Corrigendum Details
In Price Schedule in Row no. 1 to 7 Rate / Substation is derived for 1 year and in Row no. 8 Rate / Substation is derived for 3 years. Hence for better clarity to bidders, in Schedule – III ( price schedules ) on page no. 94 and 95 respectively for Regular bidder & New bidder, in tables column no. 4 header should be read as Rate / Substation / Year (Rs.) instead of Rate / Substation / 3 Year (Rs.) This is for sake of clarity only, there is no other deviation in Price Schedule.
Corrigendum Type: Clarification with regard to Rate / Substation in Price Schedule