Requirement :
|
Construction, testing and commissioning of RCC elevated service reservoir of 45 kl capacities & staging 15 mt. at bogatola including providing and fixing of ci double flange pipe, double flange specials & di double flange soft seated sluice valve including construction of suitable RCC valve chamber & providing, laying, jointing, interconnection, testing and commissioning of 90/110 mm dia pvc class 06/10 kg/sqcm pipe, 63/75 mm dia hdpe class 06 kg/sqcm pipe with suitable joints, valve specials and all fittings including all allied civil works, supply & installation of submersibles pump with control panel as required as per specifications including electric connection from cspdcl, road cutting, switch room cum pump house, information board, construction of boundary wall around the overhead tank.
|